Addison Elementary School Modernization

fs3H managed scheduling, estimating, and performed constructability reviews for Addison Elementary School.

Client

Palo Alto Unified School District

Services

Change Management, Constructability Review, Construction Management, Cost Estimating, Design Management, Schedule Management

Project Size

$18 million

Location

Palo Alto, CA

Addison Elementary School underwent a modernization of several structures where fs3H performed schedule management including baseline schedule review and monthly schedule updates, cost estimating, design management, and constructability reviews.

This project involved the removal of portable classrooms, the demolition of an existing multi-use building and the conversion of Building H to classrooms and restroom facilities. A new wood and steel framed two-story Admin/Library Building was constructed with offices, small instruction rooms, restrooms, hydraulic elevator, stairs, mechanical, warming kitchen, and storage spaces. Additionally, the project included the construction of a new wood and steel-framed high-bay, one-story multi-use building which will include two classrooms, two stages, mechanical, and storage spaces.